Waitemata DHB, Northshore Hospital Ward 8 Refurbishment, Project Manager
Project value – $1.6M NZD
Jason provided full project management of the Ward 8 refurbishment Northshore Hospital. The challenges of this project included, the ward was a live ward and was 50% occupied at all times so staging and planning of all works was critical to patient comfort and care. Service shut downs were meticulously planned, with one water shut down requiring 3x levels to be shut down for about 6hrs whist new valves were cut into the existing pipework.